The New York City Department of Buildings on Wednesday, Nov. 18, ordered the demolition of 1323 Flatbush Ave., the building right next to the Brooklyn structure that collapsed on Wednesday, Nov. 11, killing eight people. Officials concluded the building is so badly damaged that sending workers in to reinforce it is too dangerous. Before demolition begins, crews will first install shoring at 1325 Flatbush Ave. nearby.
The New York City Department of Buildings (DOB) has ordered the demolition of 1323 Flatbush Ave. in Brooklyn, the New York Post reported. The building at 1321 Flatbush Ave. collapsed on Nov. 11, killing eight people, and a joint inspection by several agencies found that the building next door suffered severe structural damage.
The collapse killed six adults and two children and injured 20 people. The Post reported that the neighboring building has been unstable since the collapse and that exposure to wind and rain has worsened its condition faster. Buildings Commissioner Ahmed Tigani said that sending workers in to carry out the extensive reinforcement needed to stabilize the structure would put them at risk, and that a controlled, safe demolition is "the only option."
Before demolition, a city contractor must install shoring at 1325 Flatbush Ave. A full vacate order remains in effect for that building. Right after the collapse, the DOB issued immediate vacate orders for 1325 and 1327. Displaced tenants are staying in hotels arranged by the city's Department of Housing Preservation and Development (HPD) and the American Red Cross through the end of November. Because the building is structurally unstable and heavily contaminated with asbestos, residents cannot go back in to collect their belongings before demolition.
According to the Post, the DOB approved an excavation plan in March for a nearby site at 2625 Bedford Ave., where a three-story, mixed-use building of about 25,000 square feet (about 2,300 square meters) was to be built. Records the Post obtained show that part of the site had elaborate bracing, but there was no heavy-duty reinforcement right next to 1321 Flatbush Ave. That same month, an inspection report that the developer's contractor submitted to the city noted cracks in the north exterior wall of 1321, and the city halted work at the site that month. The DOB is investigating six developers tied to the project.